(1) A person may apply to a local distribution company for a service connection by completing and submitting an application form provided by the distribution company.

(2) A distribution company shall provide the customer with an estimated cost of connection within

(a) five working days if the connection is to be made from an existing supply pipeline; or

(b) ten working days if tire connection requires a service line extension.

(3) Where the applicant pays tire estimated cost of connection, the distribution company shall provide supply within

(a) thirty-five working days if the connection is to be made from an existing supply pipeline; or

(b) Sixty working days if the connection requires a service line extension.