Print Options

(1) A contractor, subcontractor, licensee or other allied entity shall provide the Commission with the following information at the various stages of the bidding process:

(a) before issuing a prequalification notification to prospective bidders, the information specified in Part A of the Third Schedule;

(b) before issuing a Request for Proposals or a Request for Quotations, the information specified in Part B of the Third Schedule; and

(c) Before award of a contract or purchase order to the selected bidder, the information specified in Part C of the Third Schedule.

(2) The Commission shall confirm that a document submitted is satisfactory or otherwise provide written comments on the document submitted during the bidding process within fourteen working days of the receipt of the document.

(3) Where the Commission, without justifiable reason fails to acknowledge receipt of the documents submitted by the contractor, subcontractor, licensee or other allied entity within the period specified in sub-regulation (2), the submission shall be deemed approved.